Third Avenue Repaving Photograph Album

 Series — Box: 0
Identifier: 2613-21

Scope and Contents note

In October 1928, work began on the repaving of the deteriorating brick pavement of Third Avenue in downtown Seattle. The four-month project took place during the autumn, presenting potential weather problems, and was further complicated by the busy holiday shopping season, when both car and pedestrian traffic were heavy. Fortunately, the weather was favorable, and construction proceeded with speed and efficiency. In fact, one-way traffic was able to continue on Third Avenue during the construction, and much of the work was done before the Christmas shopping rush, opening streets up to traffic. The repaving project was completed on February 2, 1929, and was considered "...a rush work project that may be without a parallel, considering the season of the year during which the work was done."

This album compiled by the Engineering Department chronicles the repavement of Third Avenue in 1928 and 1929. The album contains approximately 140 4x6 inch prints. Included are views of Third Avenue and downtown businesses, men working, demolition of the street and railway tracks, and paving. Also included are images of machinery, automobiles, pedestrians, and men laying brick. Several photographs were taken of snow on the streets.

A fourteen-page narrative description of the project is included in the album; this report details the contract and explains work done on various dates, referring to the photographs in the album.

Approximately one-third of the images appear online in the Seattle Municipal Archives.

Dates

  • Creation: 1928-1929

Creator

Conditions Governing Access note

Records are open to the public.

Historical Note

The Engineering Department (SED) maintained the City's streets and bridges, designed and oversaw construction of public works projects, provided traffic and transportation planning, and operated the sewer and solid waste utility. The position of City Surveyor was created in 1873 to survey the City, establish boundaries and street grades, and administer condemnation processes. This position was renamed City Engineer in 1890. In 1931 the Engineering Department absorbed part of the Department of Public Utilities and in 1936 it assumed the responsibilities of the Department of Streets and Sewers and the Traffic Department. In 1997, the water, solid waste, drainage, and wastewater utilities from the Engineering and Water departments were merged with the Engineering Services Division of SED and the Customer Service Call Center and Construction Engineering Sections of City Light to form Seattle Public Utilities. The traffic and transportation functions of the Engineering Department were consolidated in the Seattle Transportation Department.

Extent

0.2 Cubic Feet (1 box)

Language of Materials

English

Abstract

Photographs of the repavement of Third Avenue, 1928 and 1929.

General Note

Third Avenue Paving Progress: Third Avenue Entrance to Post Office, November 1928. Seattle Engineering Department Third Avenue Repavement Photograph Album. Seattle Municipal Archives.

Associated Digital Objects

Title
Guide to the Seattle Engineering Department Third Avenue Repaving Photograph Album 1928-1929
Author
Finding aid prepared by Scott Cline and Shannon B. Lynch
Date
Š 2004
Description rules
Describing Archives: A Content Standard
Language of description note
Finding aid written in English.
Sponsor
Funding for encoding this finding aid was provided through a grant awarded by the National Endowment for the Humanities.
EAD Location
http://archiveswest.orbiscascade.org/ark:/80444/xv65330

Repository Details

Part of the Seattle Municipal Archives Repository

Contact:
PO Box 94728
600 Fourth Avenue, Floor 3
Seattle 98124-4728 USA US